Engineering planning implementation: Design and implement Engineering planning

The Dutch Mega Yacht builder who builds the biggest yachts of the Netherlands was struggling with their chaotic and ad-hoc engineering process causing a lot of rework and project delays.

EyeOn strengthened the Planning & Control process by designing and implementing a level 2 and level 3 Engineering planning for the yard and its contractors.

Level 2 planning templates were setup in Primavera reducing the planning setup time from 6 months to 1 day. The level 2 planning provides the time buckets for the Engineering level 3 planning on document level.

The integrated level 2 and level 3 planning setup made it possible for the yacht builder to reduce lead time with 3 months (start Basic Engineering to Delivery).